Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wds domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /vhost/wphost1/a/c/t/act.uk.net/www/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wphb domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /vhost/wphost1/a/c/t/act.uk.net/www/wp-includes/functions.php on line 6114
NHS Trust Derby | Asbestos Removal Case Study | ACT UK
Asbestos Removal For An NHS Trust in Derby

Asbestos removal for an NHS Trust

Client Requirements:

The client appointed us to undertake a large asbestos removal project to facilitate the scheduled demolition of the site. Works involved the removal of asbestos containing materials from the various buildings and subterranean structures located across the 17-acre site. The buildings ranged from single storey basement structures to a 13-storey residential tower block. This project was our highest value to date of 2.2 million pounds.

Process:

  • Initial Consultation with client
  • Site survey
  • Plan of work and pre notifications
  • Execute work
  • Project completion checks and handover

Our Solution:

Our project team created an 18-month work schedule with the client, programmed into several phases to remove all asbestos present within the buildings on the site. During our works, high risks and hazards were discovered i.e. sharp needles, unhygienic areas which was tackled by putting appropriate control measures in place. On completion of our works, the client was satisfied, and the demolition works went ahead as planned with no delays.

Testimonial – Mike Kirk, Strategic Capital Manager

We have used ACT as our Asbestos Contractor for over 10 years. They have undertaken various projects from small encapsulations to full removal on both our hospital sites in Derby. The biggest project being worth over £2,000,000. I have always found them professional and flexible and carried out all work as requested. I would have no hesitation of employing ACT Ltd again or in recommending them to any other organisation looking for reliable Asbestos contractors.