Asbestos Removal from Bilfinger Europa In Liverpool

An iconic commercial building

Client Requirements:

During the clients multi-million-pound refurbishment project of the building, we were appointed to carry out an 11-week asbestos removal programme. This involved the removal of licensed asbestos insulation board, gasket removal to pipe work and full environmental clean.

Process:

  • Initial Consultation with client
  • Site survey
  • Plan of work and pre notifications
  • Execute work
  • Project completion checks and handover

Our Solution:

A key challenge for this project was the combination of a tight deadline to coincide with a planned office move and the need to ensure a safe working environment, as the work area was surrounded by busy offices.

Thankfully, we were able to deliver a safe, fully compliant asbestos removal service in time for the planned move.