Duration: 7 weeks
Value: £220,000

Project: Asbestos was removed above all ceilings within a high street store; works included asbestos ceiling grid, plaster ceiling and encapsulation of asbestos cement. Tight time scales were set by the client due to closure of store, potential loss of revenue and re- deployment of staff.
Solution: ACT worked with the principal contractor at the planning stage implementing an achievable programme. This included working alongside other stakeholders i.e. allowing access for the refurbishment team in certain areas during our works to achieve the timescales set by the client. The project was successful with no unforeseen issues and the store was able to re open ahead of schedule.

 